Timeline

[2011] The Licensing Committee approved the building of Stage 2 of the Boardwalk from Dabush Beach to Zvulun Beach (inclusive).  The approval was given without any notice to the public or the environmental organizations and without notice to the local city council members or local planning committee.

[2012-05] Permit given to the project.

[2012-06-28] Initial construction work began in the area and was noticed by local residents who turned to Dror Ezra, a member of the regional council; to the Environmental Ministry, to Adam Teva Vedin (Israel Union for Environmental Defense), and the Society for the Protection of Nature.

[2012-07-12] Construction on the beach began.

[2012-07-26] Work was halted thanks to pressure by the above organizations on the Municipality.

[2012-07-28] The Beach March